Enter a duration
Enter the duration for the Auditor run.
The Duration setting indicates to the system the number of months prior to the current month that should be included in the Auditor run.
The default setting for the duration of months in which the Auditor run occurs is four. The Auditor is a batch process that runs on the first day of every month. If the duration is four and the Auditor is running on January, 1, 2022, the months covered in the run will be September, October, November and December of 2021.
- Open the Main Menu
and navigate to Administration > Application Setup. - Navigate to KPI Key Performance Indicator measures the result of an activity in an organization so that you can compare it to operational or strategic goals and attempt to improve performance. Builder > Auditor Setup.
- Select the Auditor Duration (Months) row and click Tap Edit.
- Enter the number of months that should be included in the Auditor run. The default number of months is four. Enter values between three and six.